Please see information below on the upcoming impacts starting on 22 July as work starts on the water main upgrades on Enterprise Street.
What will the impact be?
Lane closure will be deployed in two stages along Enterprise Street with traffic permitted one way only between the intersection with Marslin and Royal Terrace.
Turning onto Black Street from Enterprise Street will be closed periodically. Parking will me removed from the southeast side of Enterprise Street but maintained on the northwest side (outside Dunstan High School).
Lane closures will be clearly marked to ensure that motorists can navigate safely and efficiently. Please follow temporary signage posted on the streets.
When will this effect occur?
Constructions crews will arrive in July and be present in the area until September. Active work hours will be 7am to 6pm Monday to Friday.